VIEWS
ENERGY: Eskom’s Turbine Hall Project
Recent Gauteng Business News
The
Cosira Group, a South African structural steel fabricators and
construction company, has been awarded the Turbine Hall Contract for the Medupi Power
Station Project for Eskom, managed by Alstom. Cosira job in the massive construction project that is part of the multi-million
rand contract, consists of supplying 12 000 tons of steelwork.
This is the first contract that Cosira have acquired in the power generation sector, and not only that it is also the single biggest contract awarded to the supplier so far.
Cosira
is supplying the structural steel for the six units of the turbine
halls. There is also a crane building and some intermediate platforms
under construction and Cosira will be responsible for detailed shop
drawings, fabrication, corrosion protection, installation and
cladding.
“In
total the turbine hall project will require 12 000 tons of structural
steel, with each unit (turbine hall) having approximately 2000 tons.” says Richard
De Arruda, Commercial and Risk Director, Cosira.
Cosira
has purchased two 275 tonne crawler cranes for the project, in order
to overcome the limited access and time constraints of the overall
project.
Cosira
are working to a Just-in-Time (JIT) delivery methodology on site,
providing steel on-demand as the project progresses. The manufacture
and fabrication process will be carried out in phases, with batches
of steel erected on a JIT basis.
Alstom and end-customer Eskom have stringent safety
standards that must be adhered to on site, and Cosira are confident of living up to those standards. The
goal is that of Zero Harm in terms of safety, health and environmental issues.
Business News Sector Tags: Business| Energy|
|
|
||
|
Accommodation
Foreign Exchange
Directory
Fax 2 Email
Finance
Furniture
Online Casino
Restaurant
Shop Online
Study IT Online
Web Design
Weddings
Work from Home
|
||
|
Company News
|
||